## My contractor didn't pay his subs: can they put a lien on my house?

You paid in full and a subcontractor is now calling. Here is how Massachusetts mechanic's liens work, the deadlines, and what to do at each payment.

**Mateus Magno**
Licensed Construction Supervisor · November 18, 2026 · 8 min read

A finished bathroom from an Essex whole-house renovation. Photo: Magno & Co job files.

A homeowner pays the contractor, the job ends, and then a subcontractor or a supplier calls to say they were never paid. Some of them also record a paper at the registry of deeds that clouds your title. A question I hear all the time is whether that is even legal when you did nothing wrong.

The short answer is that the law lets it happen, but with limits and deadlines. This is general information, not legal advice. For your own situation, talk to a Massachusetts attorney.

## Can a subcontractor really lien my house if I paid the contractor?

It can happen. A mechanic's lien is a legal claim against the property, so the sub can go after the house even though the debt is the contractor's. The rules are in [M.G.L. chapter 254](https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254), which I read on malegislature.gov on November 18, 2026.

This is not rare enough to ignore. NBC10 Boston reported on November 12, 2026 on a renovation firm that had been a defendant in nearly 70 lawsuits, roughly 40 of them brought by subcontractors over unpaid work. According to the story, one couple ended up with three mechanic's liens on their property. I'm not naming anyone, and one story proves nothing about your contractor. It does show what the problem looks like.

If you want the lien basics for a contract you are ending, my post on [firing a contractor](https://magnoandco.com/blog-fire-contractor-massachusetts) covers them. This post goes deeper on the unpaid-sub case.

## Who can file a lien, and what has to happen first?

A lien does not appear because someone is owed money. The statute requires specific steps, and the first one is a written contract.

| Who | What they need | Where it comes from |
| --- | --- | --- |
| **Your general contractor** | A written contract with you, then a recorded notice of contract | c.254, section 2 |
| **A subcontractor, supplier, equipment renter or design professional** | A written contract with the contractor or with another sub, a recorded notice of contract, and actual notice to you | c.254, section 4 |
| **A worker owed for personal labor** | Limited to 30 days of work in the 90 days before the filing | c.254, section 1 |

For a sub, both halves matter. Section 4 says the lien arises when the notice is filed or recorded and the sub gives the owner actual notice of the filing. A paper sitting at the registry that nobody told you about is a different situation from a letter that lands on your table. Either way, don't rely on that point yourself. Ask your attorney how it applies.

MAGNO & CO

Planning a project in Somerville?

Licensed builder & owner's rep · free walkthrough · written budget in about 48 hours.

[Book a free consultation](https://calendar.google.com/calendar/appointments/schedules/AcZssZ3YJnElSsR4HsHaWVd6BsIBm7JOsDl2n-1EMy9trS9rj8PCyepopoQtl6O7um0eJcFcp5XXYk-Z)[Text me a question](sms:+19783975700?&body=Hi%20Mateus%2C%20I%20just%20read%20%22My%20contractor%20didn%27t%20pay%20his%20subs%22%20on%20magnoandco.com.%20My%20question%3A%20)[978-397-5700](tel:+19783975700)

## How much can they claim? The cap

This is the part most owners don't know. Under section 4, a sub's lien **can't exceed the amount due or to become due under the original contract as of the date the sub gives the owner notice**. The amount in the sub's own notice doesn't set the limit.

A simple illustration, not a prediction. Say your contract is $60,000 and you've paid $45,000 when notice arrives. About $15,000 is still due or to become due under that contract. A sub claiming $20,000 would, as I read the statute, be capped at that remaining amount. If you had already paid ahead of the work, you'd be in a different spot, because the cap depends on what is still owed under the contract on that date. Courts decide how that works in a real case.

There is a second cap for subs further down the chain. If a sub has no direct contract with the original contractor, its lien is limited to what is due or to become due under the subcontract of the sub above it, unless it sent a written notice of identification to the original contractor by certified mail within 30 days of starting work. That notice goes to the contractor, not to you. You may never see it.

Two more things to know. A clause in your contract that tries to bar the filing of a notice of contract or to block lien enforcement is void under section 32, so you can't rely on one. And a mistake in the amount a sub claims doesn't cancel the lien unless the sub knowingly claimed more than was due (section 11).

## What are the deadlines?

A lien is not forever. The deadlines are strict, and they start from events at the registry of deeds or from the last day of work. Here is how I read sections 4, 8 and 11.

| Step | Deadline (whichever of these comes first) |
| --- | --- |
| **1. Sub records its notice of contract** (section 4) | 60 days after a notice of substantial completion is recorded, or 90 days after a notice of termination is recorded, or 90 days after the contractor (or anyone under it) last worked or supplied material |
| **2. Sub records a statement of the amount due** (section 8) | 90 days after a notice of substantial completion, or 120 days after a notice of termination, or 120 days after the last day of work |
| **3. Sub starts a court case to enforce** (section 11) | 90 days after that statement is filed |

If the sub misses step 2 or 3, the lien is dissolved. A sub can also dissolve its own lien by recording a signed notice (section 10). A lawyer can also tell you about other ways to dissolve a lien.

There is no single "you are safe on day X" rule, and I'd distrust anyone who gives you one. Dates depend on what was recorded and when work actually stopped.

Go deeper · 30-page PDF

How to Hire a Contractor Without Getting Burned

Check any Massachusetts contractor in about ten minutes, compare bids line by line, and know what to sign and what to pay. Do it before the deposit.

[Get the guide · $15 →](https://magnoandco.com/ebook-how-to-hire-a-contractor-massachusetts)

## Before the job: what to put in place

Most of the protection happens before the first payment. This is the same groundwork I describe in my guide to [hiring a contractor](https://magnoandco.com/blog-hiring-a-contractor-massachusetts-checklist) and in the ebook [How to Hire a Contractor Without Getting Burned](https://magnoandco.com/ebook-how-to-hire-a-contractor-massachusetts).

- **Ask in writing for a list of subs and suppliers.** Names, trades and rough contract amounts. If a contractor won't tell you who is on your house, that's information.
- **Use a written contract and change orders.** Every sub's cap is tied to the original contract, so clear paperwork matters. See [what a Massachusetts contract must contain](https://magnoandco.com/blog-home-improvement-contract-massachusetts) and [how change orders work](https://magnoandco.com/blog-construction-change-order).
- **Keep the deposit small.** A big deposit is money gone before any work exists, and the lien cap doesn't help with that. See [the deposit rules](https://magnoandco.com/blog-contractor-deposit-massachusetts).
- **Check the registry of deeds.** Middlesex South covers Somerville, Cambridge, Medford and Arlington, and it posts [search instructions](https://massrods.com/middlesexsouth/search-records-instructions/). Look up your address for a recorded notice of contract.
- **Verify the license.** A registered contractor is not a guarantee of anything, but start there. See [how to check a license](https://magnoandco.com/blog-check-contractor-license-massachusetts).

## At every payment: pay for finished work and ask for waivers

A progress payment should match work you can see, not a date on the calendar. Walk the job before you pay. Under c.142A, section 2, no final payment can be demanded until the contract is completed to the satisfaction of the parties, which I also read on November 18, 2026.

Then ask for a lien waiver with each payment. Section 32 of chapter 254 contains a statutory form, "Partial Waiver and Subordination of Lien." It lists the original contract amount, change orders, work completed to date, retainage, previous payments and the amount now due, then waives liens through a stated date. It carves out retainage, unpaid change orders and disputed claims.

Here is the catch. Section 32 protects that form only for a person who recorded a notice of contract under section 2, which means your general contractor. It does not name subs, so ask your attorney how a sub's waiver is treated and what form to use. I found no statutory form for a final waiver in section 32, so ask your attorney what to use at the end.

**Builder's tip:** Keep one folder per job with the contract, every payment, every signed waiver and the sub and supplier list. If a lien notice ever shows up, the person helping you will ask for exactly that folder, and having it ready saves days.

Joint checks, made out to both the contractor and a supplier or sub, can help in the right place, such as a large material order. A joint check only covers that one payment, so it is not a substitute for waivers. Agree on it with the contractor in writing, and ask your attorney first.

## At the end of the job: final payment and the notice of substantial completion

Don't make final payment until the work is done, the punch list is closed and you hold waivers and the up-to-date sub list. Then ask your attorney about section 2A.

Section 2A says that when work is substantially complete, the owner and contractor shall record a notice of substantial completion at the registry of deeds. The owner mails a copy by certified mail, return receipt requested, to everyone who recorded a notice of contract under section 4. Recording it starts the shorter 60-day clock for new notices of contract. It is one of the few steps an owner takes part in, and it is easy to forget. The statute has the owner and the contractor both sign and record it, so you need your contractor's cooperation.

If the contract ends early, the equivalent is the notice of termination under section 2B, which I cover in the [firing post](https://magnoandco.com/blog-fire-contractor-massachusetts). And if the contractor has already vanished, start with [what to do when a contractor ghosts](https://magnoandco.com/blog-contractor-ghosted-abandoned-job-massachusetts-what-to-do).

## What if a lien notice shows up?

- **Don't ignore it, and don't panic.** Note the date you received it and keep the envelope.
- **Call a Massachusetts attorney this week.** The deadlines in section 8 and section 11 run on the sub's side, but you may need to act inside them.
- **Ask your contractor in writing.** Say what you received, ask whether the sub was paid and ask for proof and a waiver. Keep it factual.
- **Don't pay anyone twice without advice.** Paying the contractor again, or the sub directly, can be right in some cases. Get advice before you do it.
- **Gather your paperwork:** contract, change orders, payment records, waivers, sub list and the registry record.
- **Ask your attorney about your other routes.** For a contractor who took money and didn't finish, that may include the [Guaranty Fund](https://magnoandco.com/blog-massachusetts-hic-guaranty-fund), which has its own limits and rules.

## Want a second set of eyes on your job?

I'm Mateus, a licensed builder in Davis Square. Since 2020 I've renovated and managed over $5 million in projects around Somerville and Greater Boston. I'm not an attorney and I can't tell you how a lien applies to you. I can help you read a contract, set up payments tied to finished work and keep the paperwork straight. [Book a free walkthrough](https://magnoandco.com/contact) and bring your contract.

## Frequently asked questions

Can a subcontractor put a lien on my house if I paid my contractor in full?

It's possible. Under M.G.L. c.254, section 4, a subcontractor or supplier with a written contract can record a notice of contract and give you actual notice. The lien is capped at the amount due or to become due under your original contract on the date you get notice, so what you had already paid matters. Whether a lien is valid in your case is a question for a Massachusetts attorney.

How much can a subcontractor claim against me?

Section 4 caps the lien at what is due or to become due under the original contract as of the date the sub gives you notice, and the amount written in the sub's notice does not set the limit. A sub with no direct contract with the original contractor is further limited to the amount due under the subcontract above it, unless it sent a notice of identification within 30 days of starting. That is a general reading, not legal advice.

How long does a subcontractor have to file a lien?

As I read chapter 254, a notice of contract has to be recorded by the earliest of 60 days after a notice of substantial completion, 90 days after a notice of termination, or 90 days after the last day of work. A statement of the amount due follows under section 8, and a court case must start within 90 days after that statement under section 11. The exact dates depend on what was recorded, so ask an attorney.

What is a lien waiver and should I ask for one?

A lien waiver is a signed statement that the person has been paid and gives up lien rights through a stated date. Section 32 of chapter 254 includes a statutory partial waiver and subordination form, and it protects that form only for persons who recorded a notice of contract under section 2. Asking for a waiver with each payment is a sensible practice, and your attorney can tell you what form to use.

How do I check whether anyone recorded a lien or notice of contract on my property?

Search your address at your county registry of deeds. Somerville, Cambridge, Medford and Arlington are in Middlesex South, which posts search instructions on its website. Look for a recorded notice of contract or a statement of amount due. If you see one, call an attorney.

What should I do if I get a lien notice?

Don't ignore it. Keep it, note the date you received it, call a Massachusetts attorney and ask your contractor in writing whether the sub was paid. Don't pay anyone a second time without advice. Collect your contract, payment records and any waivers first.

Want someone on your side?

Text me a question or a photo, or book a free consultation: a 30-minute call or a walkthrough of your home. Licensed MA Construction Supervisor, 5.0 on Google from 9 reviews.

[Text me a question](sms:+19783975700?&body=Hi%20Mateus%2C%20I%20just%20read%20%22My%20contractor%20didn%27t%20pay%20his%20subs%22%20on%20magnoandco.com.%20My%20question%3A%20)[Book a free consultation](https://calendar.google.com/calendar/appointments/schedules/AcZssZ3YJnElSsR4HsHaWVd6BsIBm7JOsDl2n-1EMy9trS9rj8PCyepopoQtl6O7um0eJcFcp5XXYk-Z)

[Or send your project details. I reply within one business day →](https://magnoandco.com/contact#quote-form)

See [what I do as an owner's representative](https://magnoandco.com/owners-representative-somerville) and [how I price work](https://magnoandco.com/pricing).

Go deeper · 30-page PDF

How to Hire a Contractor Without Getting Burned

Check any Massachusetts contractor in about ten minutes, compare bids line by line, and know what to sign and what to pay. Do it before the deposit.

[Get the guide · $15 →](https://magnoandco.com/ebook-how-to-hire-a-contractor-massachusetts)

Read this next

- [Hiring & Planning**Can I fire my contractor? A Massachusetts homeowner's guide to ending a renovation** The crew still shows up, but the work is wrong or late and you want out. Here is the order to do it in, and where homeowners trip.9 min read · Keep reading →](https://magnoandco.com/blog-fire-contractor-massachusetts)
- [Hiring & Planning**Massachusetts home improvement contract requirements: what must be in writing** Massachusetts home improvement contract requirements under c. 142A: required terms, notices and your 3-day right to cancel, from a Somerville builder.4 min read · Keep reading →](https://magnoandco.com/blog-home-improvement-contract-massachusetts)
- [Hiring & Planning**Massachusetts contractor deposit law: how much can a contractor ask for upfront?** Massachusetts contractor deposit law in plain English: the one-third cap, the special-order exception and what a fair deposit looks like in Somerville.4 min read · Keep reading →](https://magnoandco.com/blog-contractor-deposit-massachusetts)
- [Hiring & Planning**Contractor ghosted you? A week-by-week plan for Massachusetts homeowners** Deposit paid, house half torn up, no callbacks. Here is what to do in the first 7 days and the weeks after, from a Somerville builder.9 min read · Keep reading →](https://magnoandco.com/blog-contractor-ghosted-abandoned-job-massachusetts-what-to-do)
- [Hiring & Planning**The Massachusetts HIC Guaranty Fund: who qualifies, how much it pays and how to claim** Massachusetts HIC Guaranty Fund: up to $25,000 if a registered contractor won't pay a judgment. Who qualifies and how to claim, from a Somerville builder.4 min read · Keep reading →](https://magnoandco.com/blog-massachusetts-hic-guaranty-fund)
- [Hiring & Planning**Hiring a contractor in Massachusetts: 8 checks before you sign** Registration, licenses, the written contract, the deposit and who pulls the permit — what Massachusetts law expects, in plain English.3 min read · Keep reading →](https://magnoandco.com/blog-hiring-a-contractor-massachusetts-checklist)

**Good to know:** this article is general information, not legal or engineering advice. Rules change and every property is different — confirm the details for your home with your city's building department, or [ask me](https://magnoandco.com/contact). See our [Terms & Disclaimers](https://magnoandco.com/terms).

**About the author**

Mateus Magno founded Magno & Co in 2020. He is a licensed Massachusetts Construction Supervisor (CS-123658), registered Home Improvement Contractor (HIC #220484) and certified Lead-Safe Renovator Supervisor who has renovated and managed over $5 million in projects across Greater Boston.

[More about Mateus →](https://magnoandco.com/about)

Keep reading

## More from the blog

[Hiring & Planning ### Valid license, no complaints, still a bad contractor: what the state lookup doesn't show You checked the license and it came back clean. Here is what that proves, what it can't, and six checks a Somerville builder adds before signing. 8 min read · Read article →](https://magnoandco.com/blog-contractor-license-clean-record-what-lookup-doesnt-show) [Hiring & Planning ### What Can You DIY in a Massachusetts Home? A Green, Yellow and Red List From a Builder Paint and caulk are fine. Tile showers are a gamble. Wiring, gas and structure are for licensed pros. A Somerville builder sorts the jobs. 9 min read · Read article →](https://magnoandco.com/blog-diy-or-hire-a-pro-massachusetts-green-yellow-red-list) [Hiring & Planning ### Can I fire my contractor? A Massachusetts homeowner's guide to ending a renovation The crew still shows up, but the work is wrong or late and you want out. Here is the order to do it in, and where homeowners trip. 9 min read · Read article →](https://magnoandco.com/blog-fire-contractor-massachusetts)

## Have a question about your project?

Plans, a sketch or just an idea — talk to me. You'll get honest advice and a clear written budget and schedule.

[Book a free consultation](https://calendar.google.com/calendar/appointments/schedules/AcZssZ3YJnElSsR4HsHaWVd6BsIBm7JOsDl2n-1EMy9trS9rj8PCyepopoQtl6O7um0eJcFcp5XXYk-Z) [Call 978-397-5700](tel:+19783975700) [Text me](sms:+19783975700?&body=Hi%20Mateus%2C%20I%20found%20you%20on%20magnoandco.com.%20)

Free: a 30-minute call or a walkthrough of your home.

Prefer to write? [Send me your project details](https://magnoandco.com/contact#quote-form). I reply within one business day.

[**5.0** 9 Google reviews](https://maps.google.com/?cid=2871062337128281965)

## Worked with Magno & Co?

A 1-minute Google review helps Somerville neighbors find a builder they can trust, and it means a lot to a small local business.

[Leave a Google review](https://g.page/r/CW23iOz7D9gnEAE/review) [Read our reviews on Google →](https://maps.google.com/?cid=2871062337128281965)

---
Magno & Co · licensed owner's representative and builder · 55 Davis Square, Fl 3, Somerville, MA 02145 · 978-397-5700 · info.magnoandco@gmail.com · MA CSL CS-123658 · MA HIC #220484 · https://magnoandco.com/