# Massachusetts Contractor Deposit Law: The One-Third Rule

Page: https://magnoandco.com/blog-contractor-deposit-massachusetts

> Massachusetts contractor deposit law in plain English: the one-third cap, the special-order exception and what a fair deposit looks like in Somerville.

Hiring & Planning

## Massachusetts contractor deposit law: how much can a contractor ask for upfront?

Massachusetts contractor deposit law in plain English: the one-third cap, the special-order exception and what a fair deposit looks like in Somerville.

**Mateus Magno**
Licensed Construction Supervisor · November 2, 2026 · 4 min read

Quick answer

Under M.G.L. c. 142A, section 2, a Massachusetts home improvement contractor cannot take an advance deposit larger than one-third of the total contract price, or the actual cost of special-order or custom materials that must be ordered before work starts, whichever is greater. The deposit belongs in a signed written contract, and final payment cannot be demanded until the work is complete.

The Massachusetts contractor deposit law is short and clear: before work starts, a home improvement contractor can ask for no more than **one-third of the total contract price**, unless special-order materials cost more. I sign contracts under this rule in Somerville, Cambridge and Medford, so here is how it works in real life.

The rule lives in [M.G.L. c. 142A, section 2](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXX/Chapter142A/Section2), the state's Home Improvement Contractor law. If someone asks for half or more upfront on a normal remodel with no special orders, treat it as a red flag.

## What the Massachusetts contractor deposit law says

Section 2 says an advance deposit cannot exceed the **greater** of:

- **One-third of the total contract price**, or
- The **actual cost of special-order or custom-made materials** that must be ordered before work begins so the project stays on schedule.

The same section adds two payment rules that go hand in hand with the deposit cap:

- The contract needs a **payment schedule** that states each payment in dollars, including any finance charges.
- The contractor **cannot demand final payment** until the work is completed to the satisfaction of the parties.

The state's Office of Consumer Affairs and Business Regulation (OCABR) repeats the rule on its [contract requirements page](https://www.mass.gov/info-details/home-improvement-contract-requirements-details-and-sample-language), and its sample contract puts a deposit line right at the top of the payment schedule.

## Who the deposit rule covers

Chapter 142A covers work on a **pre-existing, owner-occupied building with one to four dwelling units**, per the definitions in [section 1](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXX/Chapter142A/Section1). That includes most single-families, two-families and owner-occupied triple-deckers around Davis Square, Union Square and East Somerville. Brand-new construction falls outside that definition.

Any contract over **$1,000** must be in writing, and the deposit rule only protects you fully when the contractor is registered. You can check any contractor's registration on the state's [MA Contractor Hub](https://contractorhub.mass.gov/s/), or follow my guide on [checking a contractor's license in Massachusetts](https://magnoandco.com/blog-check-contractor-license-massachusetts).

MAGNO & CO

Planning a project in Somerville?

Licensed builder & owner's rep · free walkthrough · written budget in about 48 hours.

[Book a free consultation](https://calendar.google.com/calendar/appointments/schedules/AcZssZ3YJnElSsR4HsHaWVd6BsIBm7JOsDl2n-1EMy9trS9rj8PCyepopoQtl6O7um0eJcFcp5XXYk-Z)[978-397-5700](tel:+19783975700)

## What is a reasonable deposit for a contractor?

For most remodels, a reasonable deposit is **up to one-third**, and often less. Here is the math on a made-up example: on a $60,000 contract, the cap is **$20,000**. The only way it goes higher is if custom items that must be ordered before demolition actually cost more than $20,000.

What I consider fair, from my own jobs:

- **Small repairs:** a small deposit or none, because there is little to order.
- **Kitchens and baths:** a deposit sized to the cabinets, tile, windows or fixtures with long lead times.
- **Gut renovations and additions:** a deposit, then progress payments tied to milestones the inspector can see.

## The special-order exception, explained

Custom cabinets, made-to-measure windows and special-order doors often need money before anyone picks up a hammer. That is what the exception is for. To use it the right way:

- List each special-order item in the contract with its **dollar amount**. OCABR's sample contract has a section built for exactly this.
- Ask for the supplier quote or order confirmation.
- Make sure the item really has to be ordered before work starts. Standard stock items do not qualify.

## How progress payments should work

After the deposit, every payment should match work you can see. Section 2 also bans **acceleration clauses** that let a contractor call the whole balance due because they feel "insecure." If a contractor has a real concern, the law lets them ask that the remaining funds go into a **joint escrow account** instead.

- Deposit at signing (within the cap).
- Payments at milestones such as demolition done, rough inspections passed, drywall finished.
- Final payment after the punch list and final inspections.

**Builder's tip:** Tie payments to milestones, not calendar dates. In a 1920s triple-decker the schedule can slide once we open a wall, but "rough plumbing and electrical inspections passed" means the same thing no matter what week it happens. It keeps everyone honest, including me.

## Red flags when a contractor asks for money upfront

- **Half or all of the price before starting**, with no special-order list to explain it.
- **No written contract**, or no HIC registration number on it. OCABR says the number belongs on the first page.
- **"You pull the permit."** Under section 2, homeowners who pull their own permits are excluded from the state Guaranty Fund.
- **Pressure to sign today.** If you sign at home, [M.G.L. c. 93, section 48](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXV/Chapter93/Section48) gives you until midnight of the third business day to cancel in writing.

My [contractor hiring checklist](https://magnoandco.com/blog-hiring-a-contractor-massachusetts-checklist) covers the rest of what to check before you sign.

## What if you already paid too much?

Put your concern in writing to the contractor first and keep copies of every payment. If that goes nowhere, OCABR runs a consumer hotline at (617) 973-8787, and homeowners can bring disputes with registered contractors to a state-approved arbitration program under [section 3](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXX/Chapter142A/Section3). For your specific situation, talk to a lawyer.

## Need a hand?

I write every contract with a clear deposit, a special-order list and milestone payments. [Book a free walkthrough](https://magnoandco.com/contact) and I will send a written line-item budget, usually within 48 hours. I work in Somerville, Cambridge and across Greater Boston.

## Frequently asked questions

What is the maximum deposit a contractor can ask for in Massachusetts?

Under M.G.L. c. 142A, section 2, the deposit cannot exceed one-third of the total contract price or the actual cost of special-order or custom materials that must be ordered before work starts, whichever is greater.

What is a reasonable deposit for a contractor?

For most home renovations in Massachusetts, a reasonable deposit is up to one-third of the contract price, and often less on small jobs. Anything higher should be backed by a written list of special-order items and their costs.

Can a contractor ask for 50% upfront in Massachusetts?

Only if special-order or custom materials that must be bought before work begins actually cost that much. Otherwise the law caps the advance deposit at one-third of the total price.

Does the one-third deposit rule apply to new construction?

Chapter 142A covers work on pre-existing, owner-occupied buildings with one to four units, so brand-new construction is outside that definition. Renovations and additions to an existing owner-occupied home are covered.

**Want someone on your side?** See [what I do as an owner's representative](https://magnoandco.com/owners-representative-somerville) and [how I price work](https://magnoandco.com/pricing).

**Good to know:** this article is general information, not legal or engineering advice. Rules change and every property is different — confirm the details for your home with your city's building department, or [ask me](https://magnoandco.com/contact). See our [Terms & Disclaimers](https://magnoandco.com/terms).

**About the author**

Mateus Magno founded Magno & Co in 2020. He is a licensed Massachusetts Construction Supervisor (CS-123658), registered Home Improvement Contractor (HIC #220484) and certified Lead-Safe Renovator Supervisor who has renovated and managed over $5 million in projects across Greater Boston.

[More about Mateus →](https://magnoandco.com/about)

Keep reading

## More from the blog

[Hiring & Planning ### Massachusetts home improvement contract requirements: what must be in writing Massachusetts home improvement contract requirements under c. 142A: required terms, notices and your 3-day right to cancel, from a Somerville builder. 4 min read · Read article →](https://magnoandco.com/blog-home-improvement-contract-massachusetts) [Hiring & Planning ### Buying an old house that needs work: a Somerville, Cambridge and Medford checklist Buying an old house that needs work in Somerville, Cambridge or Medford? My builder's checklist: what to inspect, lead and permit lookups, how to budget. 4 min read · Read article →](https://magnoandco.com/blog-buying-old-house-somerville-renovation) [Hiring & Planning ### EV charger installation rebate in Massachusetts: Level 2 charging at home in Somerville EV charger installation rebate Massachusetts guide: Eversource and National Grid 2026 offers, Somerville permits, Level 2 costs and condo charging rights. 4 min read · Read article →](https://magnoandco.com/blog-ev-charger-installation-massachusetts)

## Have a question about your project?

Plans, a sketch or just an idea — talk to me. You'll get honest advice and a clear written budget and schedule.

[Book a free consultation](https://calendar.google.com/calendar/appointments/schedules/AcZssZ3YJnElSsR4HsHaWVd6BsIBm7JOsDl2n-1EMy9trS9rj8PCyepopoQtl6O7um0eJcFcp5XXYk-Z) [Call 978-397-5700](tel:+19783975700)

## Worked with Magno & Co?

A 1-minute Google review helps Somerville neighbors find a builder they can trust, and it means a lot to a small local business.

[Leave a Google review](https://g.page/r/CW23iOz7D9gnEAE/review) [Read our reviews on Google →](https://maps.google.com/?cid=2871062337128281965)

---
Magno & Co · licensed owner's representative and builder · 55 Davis Square, Fl 3, Somerville, MA 02145 · 978-397-5700 · info.magnoandco@gmail.com · MA CSL CS-123658 · MA HIC #220484 · https://magnoandco.com/